New University Hospital
University Hospital 2026

A new university hospital

Let's build the university hospital of tomorrow together!

A thoroughly redesigned architectural organization to improve the response to patients' needs.

  • Grouping services around platforms to streamline processes by bringing the professional to the patient.
  • Designing architecture around hotel quality (individual rooms), space planning (greening of exteriors, direct access to light in all spaces), and the human dimension from reception to the patient's room.
Surface

111000

total area

beds and places

1397

beds and places

85% in single rooms
operating rooms

35

operating rooms

medical imaging rooms

26

medical imaging rooms

total budget

600

total budget

New University Hospital of Caen Normandy
Biology · Research

Biology · Research

Services
  • Territorial University Institute of Biology and Health
  • Research and Innovation Department
Logistics · Pharmacy · Administration

Logistics · Pharmacy · Administration

Services
  • General Management
  • Directions
    • Infrastructure and reconstruction
    • Digital and information system transformation
    • Purchasing and logistics
    • Medical Affairs
    • Human Resources
    • Care
    • Financial Affairs
    • Legal matters
    • General Affairs
    • Quality
    • Communication
  • Medical Establishment Committee
  • Pharmacy
The family home

Care

IPA
  • Institute for the Elderly
Care

Care

Stays
  • Conventional hospitalization
  • Education
Dentistry

Care

Dentistry
  • Consultations
  • Interventions
  • Education
Ribbon

Care

ICNO
  • Normandy West Cancer Institute
Care

Care

Welcome
  • Outpatient hospitalization
  • Consultations
Care

Care

Reviews
  • Technical platform
  • EMERGENCIES
Parking

Parking

Large capacity
Heliport

Heliport

platform state-of- the-art

  • By 2026, the surgical and interventional activity platforms will allow for the development of the use of the latest minimally invasive techniques, robotics or artificial intelligence.
  • The consolidation of biological will, through automation,for a better response to emergencies and, through genomic sequencing, improve the integration of prevention into diagnosis.
  • Over the same period, imagingwill be the subject of investments in order to improve equipment and enable a digital transformation of imaging activities and the use of latest generation equipment.
  • From 2023, the pharmacy will benefit from modernized platforms and equipment, including storage and distribution, and an innovative preparation platform, a benchmark in western Normandy.

A capacity evolution adapted to the needs of the territory

  • Maintaining current hospital capacity while adapting to the aging population
  • Increase the number of outpatient places
  • Create an additional critical care unit
  • To streamline downstream care through a post-acute and medical care center on the Clemenceau site, which aims to be more open to the city

A digital transformation for all medical, caregiving, administrative, logistical and technical activities

To generalize the seamless and secure sharing of health data between professionals and users

Implement in the short term new solutions that should simplify the patient experience and the work of professionals (mobile application for monitoring and booking appointments, administrative management, etc.).

  • In the medium term, improving the collection, quality and availability of health data will open up new fields of application for research,
    diagnosis and care (data warehouse, data processing techniques, innovations…).

building environmentally conscious incorporating sustainable development approaches

process High Environmental Quality certification which aims to:

  • Controlling the impacts of a building on its external environment;
  • The preservation of natural resources;
  • Creating a healthy and comfortable indoor environment for building users.

This approach extends throughout the entire institutional project through reflection on eco-responsible organizations and practices: waste management, sustainable mobility, energy efficiency with the use of renewable energies, the use of less energy-intensive materials, green roofs or even eco-responsible catering.

The attention paid to the expectations of patients, users and families is reflected throughout the entire institutional project, through considerations of accessibility, simplification of administrative processes and development of the patient experience.

Next steps

What are the next steps?

Works

March/April 2023

Arrival of the first crane to begin the main construction work.

Delivery

End of April

building LPA, gradual move-in (logistics then administration then pharmacy)

demolition

From May 2023

Asbestos removal and demolition of the current general store

elevations

From July 2023

Construction of the walls and floors of the main structure begins. This phase lasts 1 year.

dentistry

October 2023

Opening of the dental building

silo parking

End of October 2023

Opening of the 850-space parking garage

structural work

June 2024

The main structural work on the South accommodation building is complete

structural work

Summer 2024

The structural work on the HDJ
structural work

January 2025

The main construction work on the medical-technical platform is complete
structural work

May 2025

The main structural work on the North accommodation building is complete
Reception

The main operation is scheduled for completion at the end of November 2026